承攬工程實績
[1][2][3][4][5][6][7][8][9][10]


業主:中國石油股份有限公司桃園煉油廠
Client:Chinese Petroleum Corp. Taoyuan Refinery
工程名稱:桃廠第二重組工場空氣冷卻器、鋼架製作安裝工程(26 SETS、2236T)
Job Description:Manufacturing and installation of air cooler and steel structure for NO.2 reformer at Taoyuan Plant (26 SETS、2236T)
開工:1993.05.03
Commencement Date:1993.05.03
完工:1994.12.03
Completion Date:1994.12.03
特殊情形:含AIR COOLER、對心、噪音、振動值測試合格;鋼構、設備支架輕質防火材施工。
Special Circumstances:Include approved results of tests of air cooler, heart, noise, and vibration. Construction of steel structure, equipment holders, and lightweight fire prevention materials.

 



業主:中國石油股份有限公司桃園煉油廠
Client:Chinese Petroleum Corp. Taoyuan Refinery
工程名稱:桃廠第二重組工場空氣冷卻器、鋼架製作安裝工程(26 SETS、2236T)
Job Description:Manufacturing and installation of air cooler and steel structure for NO.2 reformer at Taoyuan Plant (26 SETS、2236T)
開工:1993.05.03
Commencement Date:1993.05.03
完工:1994.12.03
Completion Date:1994.12.03
特殊情形:含AIR COOLER、對心、噪音、振動值測試合格;鋼構、設備支架輕質防火材施工。
Special Circumstances:Include approved results of tests of air cooler, heart, noise, and vibration. Construction of steel structure, equipment holders, and lightweight fire prevention materials.

 


業主:中國石油股份有限公司桃園煉油廠
Client:Chinese Petroleum Corp. Taoyuan Refinery
工程名稱:桃廠第二重組工場空氣冷卻器、鋼架製作安裝工程(42 SETS、1061T)
Job Description:Manufacturing and installation of air cooler and steel structure for NO.2 reformer at Taoyuan Plant (42 SETS、1061T)
開工:1992.08.17
Commencement Date:1992.08.17
完工:1994.11.23
Completion Date:1994.11.23
特殊情形:含AIR COOLER、對心、噪音、振動值測試合格;鋼構、設備支架輕質防火材施工,工程金額共NT$82,761,025。
Special Circumstances:Include approved results of tests of air cooler, heart, noise, and vibration. The total cost for construction of steel structure holders, and lightweight fire prevention materials is NT$82,761,025.

 


業主:中國石油股份有限公司桃園煉油廠
Client:Chinese Petroleum Corp. Taoyuan Refinery
工程名稱:桃廠第二重組工場空氣冷卻器、鋼架製作安裝工程(42 SETS、1061T)
Job Description:Manufacturing and installation of air cooler and steel structure for NO.2 topping at Taoyuan Refinery (42 SETS、1061T)
開工:1992.08.17
Commencement Date:1992.08.17
完工:1994.11.23
Completion Date:1994.11.23
特殊情形:含AIR COOLER、對心、噪音、振動值測試合格;鋼構、設備支架輕質防火材施工,工程金額共NT$82,761,025。
Special Circumstances:Include approved results of tests of air cooler, heart, noise, and vibration. The total cost for construction of steel structure holders, and lightweight fire prevention materials is NT$82,761,025.

業主:中國石油股份有限公司林園石化廠
Client:Chinese Petroleum Corp. Linyuan Petrochemical Plant
工程名稱:大林廠第二二甲苯工場空氣冷卻器安裝工程(72 SETS)
Job Description:AIR COLLER INSTRLLATION OF 2ND TOLUENE PLANT OF LIN YUAN PLANT
開工:1992.04.06
Commencement Date:1992.04.06
完工:1992.10.20
Completion Date:1992.10.20


業主:中國石油股份有限公司林園石化廠
Client:Chinese Petroleum Corp.? Linyuan Petrochemical Plant
工程名稱:大林廠第二二甲苯工場空氣冷卻器安裝工程(72 SETS)
Job Description:AIR COLLER INSTRLLATION OF 2ND TOLUENE PLANT OF LIN YUAN PLANT
開工:1992.04.06
Commencement Date:1992.04.06
完工:1992.10.20

Completion Date:1992.10.20